We’ve earned a grant to put a bike repair station, pump, bike racks, and picnic tables out front!!
Pretty please, I need help with several stages:
(Weather permitting)
receiving the concrete delivery at LMN (6/30)
digging and framing concrete pad (7/1)
-please bring in your own shovel
picking up concrete mixer rental from Menards(7/2)
pouring concrete (7/2)
returning concrete mixer (7/2)
(Dates tbd)
Removing concrete frame
Installing bike repair station and pump
Picking up picnic table materials (truck required)
Cutting up picnic table materials
Building picnic tables
Whatever I forgot
Please reply here with what stage you wish to help with
Pizza will be provided digging and pouring concrete. Please let me know if dietary restrictions
Currently doing the math, and layout requirements for the repair station and bike rack
I requested 19 60# bags of concrete in the original green, plus a mixer rental, and the slab should be at least 3" thick
So, 12 ish square feet max size, probably smaller